31
(6)
feet in length through Smugglers Ridge and the South Tunnel 4,689 feet in length through Golden Hill were
completed, and so also was the reservoir with a
capacity of 33 million gallons in the lower Shek-
lai-pui valley, built to receive raw water delivered
through these tunnels. In the following year 150
feet of the North Tunnel were straightened and 3,200
feet of 24" steel main were laid. This trunk main
will bring the Sheng-mun water to Kowloon Point and
will have a total length of 24,030 feet with a feed
to the Kowloon distribution system at Pipers Hill,
where a covered reinforced concrete service reservoir
with a capacity of là million gallons was completed
in 1925. Immediately below the reception reservoir
in the lower Shek-lai-pui valley is the site of a rapid gravity filtration plant to deal ultimately with 20 million gallons a day. The first section of
this plant capable of filtering five million gallons
a day has already been completed and is now in operation.
Adjoining these filters, there is under construction a
covered reinforced concrete service reservoir with a
capacity of eleven million gallons".
In order that the water from the Sheng-mun
scheme may be available on Hong Kong Island, further works estimated at cost $361,602 must still be
completed, including a pipe-line across the harbour described in the Memorandum circulated with C.D.A.C.31
(2)
Estimated Total Cost.
(a) Aberdeen Scheme
Developments of Scheme Resumption and
Salvage
$2,177,000
525.000 $2,702,000
(b)
No comments yet.
Private notes are available after approval.